slug: user-preferences
title: User Preferences API
created: 2026-02-09T02:15:19.934404761Z
phase: merge
phase_history:
- phase: draft
entered: 2026-02-09T02:15:19.934404761Z
exited: 2026-02-09T02:18:19.466533103Z
- phase: specified
entered: 2026-02-09T02:18:19.466533103Z
exited: 2026-02-09T02:29:25.185315477Z
- phase: planned
entered: 2026-02-09T02:29:25.185315477Z
exited: 2026-02-09T02:29:30.58699614Z
- phase: ready
entered: 2026-02-09T02:29:30.58699614Z
exited: 2026-02-09T02:32:28.709423195Z
- phase: implementation
entered: 2026-02-09T02:32:28.709423195Z
exited: 2026-02-09T02:42:14.015835526Z
- phase: implementation
entered: 2026-02-09T02:42:14.015835526Z
exited: 2026-02-09T02:45:34.10464457Z
- phase: review
entered: 2026-02-09T02:45:34.10464457Z
exited: 2026-02-09T02:47:54.348498546Z
- phase: audit
entered: 2026-02-09T02:47:54.348498546Z
exited: 2026-02-09T02:54:39.358387814Z
- phase: qa
entered: 2026-02-09T02:54:39.358387814Z
exited: 2026-02-09T02:54:44.440652677Z
- phase: merge
entered: 2026-02-09T02:54:44.440652677Z
artifacts:
audit:
status: passed
path: audit.md
design:
status: approved
path: design.md
approved_by: user
approved_at: 2026-02-09T02:23:50.511364172Z
qa_plan:
status: approved
path: qa-plan.md
approved_by: user
approved_at: 2026-02-09T02:29:20.545684043Z
qa_results:
status: passed
path: qa-results.md
review:
status: passed
path: review.md
spec:
status: approved
path: spec.md
approved_by: user
approved_at: 2026-02-09T02:18:15.533898188Z
tasks:
status: approved
path: tasks.md
approved_by: user
approved_at: 2026-02-09T02:26:14.114770656Z
total: 6
completed: 6
tasks:
- id: task-001
title: Domain layer - preferences entity, validation, defaults, and errors
status: complete
started_at: 2026-02-09T02:32:33.046963423Z
done_at: 2026-02-09T02:33:13.805844526Z
- id: task-002
title: Port layer - PreferencesRepository interface
status: complete
started_at: 2026-02-09T02:33:13.812394852Z
done_at: 2026-02-09T02:33:27.291639357Z
- id: task-003
title: Service layer - PreferencesService with deep merge, get/update logic, and unit tests
status: complete
started_at: 2026-02-09T02:33:27.300268305Z
done_at: 2026-02-09T02:34:22.01529497Z
- id: task-004
title: Database migration and PostgreSQL adapter
status: complete
started_at: 2026-02-09T02:34:22.023308991Z
done_at: 2026-02-09T02:34:49.980516171Z
- id: task-005
title: HTTP handlers - GET and PUT preferences with request/response types and unit tests
status: complete
started_at: 2026-02-09T02:34:49.9863189Z
done_at: 2026-02-09T02:35:44.499210123Z
- id: task-006
title: Wiring, routes, OpenAPI spec, and example scaffolding removal
status: complete
started_at: 2026-02-09T02:35:44.505187642Z
done_at: 2026-02-09T02:37:21.440542135Z